According to DMTCL sources, on August 29, for the first time, Metrorail will run a test run from Diabari Depot to Mirpur Station No. 12 with six bogies. Since then, the experimental journey has been going on regularly. This time in the month of victory, Metro Rail will run trial run from Uttara to Agargaon in December.

Passengers will not be transported during the experimental operation. However, after the official inauguration, a maximum of 2,308 passengers will be able to board and board a train. This metrorail is fully electric. 16-18 systems including signals and communication work in running trains.

According to the project progress report, the overall progress of the project has been 72 percent till last November. The progress of the previous work from Uttara to Agargaon is 69.61 percent. The entire project will be completed in 2024.

Please Share This Post in Your Social Media

Leave a Reply

Your email address will not be published.




© All rights reserved © 2022 Jonotaralo
Design BY NewsTheme